Construction The Douglas Crossroads intersection will be upgraded to a Roundabout. Construction began in February of 2024. Traffic will be maintained during the course of the project, with several lane closures and traffic shifts as the project progresses. As of Monday April 8th, 2024, traffic at the Douglas Crossroads Intersection was shifted to a new traffic pattern. Designated turn lanes and the caution lights at the intersection have been removed. Vehicles are advised to lower speed and follow all work zone traffic control signs and devices.
Us-264 E / US Highway 264 E - Washington, NC
Starts at Feb 12, 2024 12:00pm Until: Nov 12, 2024 10:00pm Severity: Moderate